The 500kV line has a capacity of carrying up to 2,000 megawatts and is 1,055Km long

Sep 28 , 2019
By YOSEPH MERGU ( FORTUNE STAFF WRITER )


Built by China Electric Power Equipment and Technology (CET), the project connects the Kenyan and Ethiopian power grids.

The Ethiopian part of the 1.26-billion-dollar Eastern Electricity Highway Project that connects Ethiopia with Kenya is set to be completed next month.

Built by China Electric Power Equipment and Technology (CET), the project connects the Kenyan and Ethiopian power grids.

The high voltage electric line, which is a result of the joint venture of the two countries, has a capacity of carrying up to 2,000 megawatts and covers 1,055Km, while 433Km of the total electric highway lies within Ethiopian borders.



The construction of the power transmission line has already been completed in August 2019, and the highway is only awaiting finalisation of the construction of a substation, according to Moges Mekonnen, communication director of Ethiopian Electric Power (EEP).


After the construction of the substation is completed, the testing will be implemented within five months, and the highway will be ready for power transmission by April 2020.

Wolayta Sodo is the starting point for the 500kV line, and the overhead transmission lines are supported by approximately 38m-high and 15m-wide steel towers and sit on 4m-deep reinforced concrete foundations. The width of the line corridor ranges between 50m and 60m.




From the overall investment in the project, the World Bank provided a loan of 684 million dollars, while the African Development Bank and the French Development Agency are providing 338 million dollars and 118 million dollars, respectively.

The government of Ethiopia and the government of Kenya funded 32 million dollars and 88 million dollars, respectively.


The construction of the remaining part of the highway in Kenya is being carried out by the German company Siemens Transmission & Distribution. The work has begun from the Suswa substation in western Kenya.

Upon its completion, the project is expected to generate investment opportunities in electricity infrastructure and also gives rise to the development of other related industries.

Ethiopia currently generates 4,300MW of power, of which 90pc is produced from hydropower, while eight percent is generated from wind, and two percent is generated from thermal sources.

Ethiopia is endowed with a huge hydro generation potential, which is estimated at approximately 45,000 MW.


A hydropower expert appreciated the construction of the transmission line between the two countries.

“Construction of the transmission line is important, not only to sell but also to buy electric power when we face a shortage of supply,” Tigabu Atalo, an energy practitioner, told Fortune.

According to the expert, this is helpful for regional integration and interconnecting African countries through power.

“We must be well advised on the power purchase agreement schedule for the delivery of electricity, penalties for under-delivery and on tariff allocation.

Currently, the construction of the Grand Ethiopian Renaissance Dam (GERD) being built on the Abay River in Benshangul Gumuz Regional State has reached 68.3pc completion.



PUBLISHED ON Sep 28,2019 [ VOL 20 , NO 1013]


How useful was this post?

Click on a star to rate it!

Average rating 0 / 5. Vote count: 0

No votes so far! Be the first to rate this post.





Editors' Pick



Editorial




Back
WhatsApp
Telegram
Email